Morong, Rizal - Integrated Solid
Waste Management Facility



The Morong Integrated Solid Waste Management Facility is a component under the Waste Management and Sanitation program of the Local Government Unit of Morong in Rizal Province. The facility is implemented with assistance of the World Bank, Netherlands Government and LLDA through the LISCOP project. It is designed to recover reusable and recyclable materials from collected municipal solid wastes. It will accomplish this by reducing the volume of waste that ends up in the landfill by converting it to products used by the community.

Objective of the Project: To provide the municipality of Morong with the technology needed for proper solid waste processing in order to manage systematically the collection, segregation, processing, transfer, storage and marketing of processed waste product.

The project includes:

Waste Segregation Center- Here, waste is sorted to recover the recyclable components including plastic, glass, leather and metals.

• Compost and organic fertilizer plant - In this facility, the biodegradable fraction of the waste is segregated, shredded, and then composted to produce a soils amendment used by local farmers and gardeners.

• Plastic Recycling Center- In this facility, plastic products are removed from the solid waste stream and sorted by composition and sent to various markets throughout the Metro Manila area where they are sold to local venders. Some of the plastics are shredded for incorporation into hollow blocks production.

• Hollow Block Manufacturing Plant - This facility mixes sand, gravel, cement and shredded plastics to produce construction grade concrete blocks used in the local building industry.

Beneficiaries of the Project: The households and commercial establishments including schools, churches and other offices along and near the collection routes are the project beneficiaries. In terms of additional income, the hired personnel of the facility and the local government will benefi t from the project. More importantly for the community, the project creates a cleaner and healthier environment for the people of Morong and the overall watershed of Laguna de Bay.

The compost - organic fertilizer plant is a major component of the facility in terms of personnel and area covered. It will occupy 430 sq. meters and include the equipment for preparing the compost as well as packaging it for resale. The compost will be a major income component of the project from the sales of organic biodegradable materials. Once processed, the composed organic material will be mixed, pelletized, dried, and then placed in bags or bins for reselling.

Total Value of the Project: P9,929,690.75 Grant: P3,971,876
Loan: P4,468,361 LGU Equity 7.5% LLDA Equity: 7.5%
Project Completion Date: January 15, 2008

3 comments:

Unknown said...

Your post is good but the information is lacking.. say information about the contact person, number, address etc. where people can inquire about their products

Unknown said...

I'm interested with the paving blocks from Morong. To whom should we contact? Are they still manufacturing the blocks? Was this project sustained?

kelvin said...

yeah that was nice.thank you.........http://www.green4care.com